BACKGROUND SUMMARY: | We had appropriated 3 Million dollars for construction of a new Public Service facility. After initial discussions with the Hybrid Engineering team, negotiations stalled. Approximately $200,000 was spent on civil engineering fees and designs. We recently re-engaged the project opting for a design build. Four (4) companies provided proposals, Mashburn Construction, Gilbert Construction, GMK associates and Camden Construction. After reviewing the proposals, Camden Construction's team is the recommended company to construct our Public Service facility. |
| | | |